Mechanical assembly of structures, high-pressure applications, equipment and everything included in the Boiler Area.
Mechanical assembly of fumes and chimney structure.
Installation on site of carpentry, casing machinery in reference to the Russi Line of biomass fumes treatment.
Mechanical implementation of the Biomass Handling System.
Implementation of the Piping Supports and Equipment.
Tubing installation.
Supply of materials, prefabrication and assembly of pipe STAND PIPI DEAERATOR.
Prefabrication and installation of piping supports.
Tank installation.
Project implemented on behalf of Termokimik Corporation S.p.A. at the PowerCrop Power Plant in Russi (RAVENNA).